Neelum-Jhelum Hydropower Plant based in Muzzafarabad will produce electricity?

A969 Mwt
B4500 Mwt
C425 Mgw
D3200 Mwt

Choose an option to check yourself, or reveal the answer and explanation instantly.

Related Current Affairs MCQs

View all

Test Yourself

Take a full quiz on Current Affairs

Start Quiz

Exam Coverage

FPSCNTSCSSPPSC

Trust

Answer is visible after reveal
Explanation helps learning
Free topic quiz available

Subject

Current Affairs

Save your progress

Create a free account to bookmark MCQs and track weak areas.

Register Free
Start QuizMore MCQs
Answer and explanation

Correct Answer: A: 969 Mwt

Explanation: The correct answer is A: 969 MWt. The Neelum-Jhelum Hydropower Plant is a run-of-river project located near Muzaffarabad, Azad Kashmir, with an installed capacity of 969 MW. It is one of Pakistan's largest hydropower projects and uses the waters of the Neelum River before they enter the Jhelum River.

Neelum-Jhelum Hydropower Plant based in Muzzafarabad will produce e...